by JuicyAdmin | Apr 1, 2007
We established the project organisation and quality management procedures on this £52m re-signalling contract in advance of the main installation works. With growing passenger numbers, London Underground needed to increase the capacity on their network. In addition to...
by JuicyAdmin | Apr 1, 2004
We executed a critical design programme with stakeholders to achieve a unique Safety Case on the £120m nuclear submarine berthing facility, and reconciled contract variations on behalf of the lead consultant, negotiating £2.1m in additional design fees. The new...